The OAK311 mobile app and SeeClickFix web portal will be down from Thursday February 13th at 7:00 pm to Saturday February 15th at 11:59pm for a software update. During this time, we will only be responding to infrastructure emergencies. To report an infrastructure emergency, please call us by dialing 3-1-1 (if in Oakland) or (510) 615-5566.

Mini Parks Beautification Project

The City of Oakland has renovated and beautified nine mini parks throughout the City's historically underserved communities, enriching each site for Oakland youth and families to enjoy.

Status:
Completed
Start date:
Oct 21, 2022
Completion date:
Dec 31, 2024

About

The City of Oakland has completed a $4.9 million dollar project improving and beautifying nine mini parks citywide: 

  1. 88th Avenue Mini Park (1803 88th Avenue)
  2. Cesar Chavez Mini Park (1800 38th Avenue)
  3. Eula Brinson Mini Park (1712 85th Avenue)
  4. Gwen Jackson Mini Park (3042 Nicol Avenue)
  5. Lazear Mini Park (850 29th Avenue)
  6. McClymonds Mini Park (2528 Linden Street)
  7. Morgan Plaza (2601 Highland Avenue)
  8. Tomás Melero-Smith Mini Park (1461 65th Avenue)
  9. Vantage Point Park (1198 13th Avenue)

The project re-surfaced play areas, added new park furniture, accessible seating, and BBQ pits to all nine parks. Six of the nine parks received brand new code compliant play equipment. New drinking fountains have been installed to reduce consumption of sugary beverages and use of disposable plastic bottles.  Dozens of shade trees have been planted to reduce the urban heat island effect, and parks have been greened with new landscaping and irrigation. The parks were also updated with new lighting, fencing, and gates to increase safety, and new animal-proof trash receptacles have been installed to encourage proper litter disposal and deter illegal dumping. These enhancements have significantly improved and beautified the parks, expanding access to recreation and creating new opportunities for community connection. 

Map

Map of Project: Mini Parks Beautification Project
Map of Project: Mini Parks Beautification Project

88th Avenue Mini Park

Map of Project: Mini Parks Beautification Project

Cesar Chavez Mini Park

Map of Project: Mini Parks Beautification Project

Eula Brinson Mini Park

Map of Project: Mini Parks Beautification Project

Gwen Jackson Mini Park

Map of Project: Mini Parks Beautification Project

Lazear Mini Park

Map of Project: Mini Parks Beautification Project

McClymonds Mini Park

Map of Project: Mini Parks Beautification Project

Morgan Plaza

Map of Project: Mini Parks Beautification Project

Tomas Melero-Smith Mini Park

Map of Project: Mini Parks Beautification Project

Vantage Point Park

Timeline

Planning - Consultant Selection
October 2022 - March 2023
Design
March 2023 - November 2023
Bid/Award
November 2023 - January 2024
Drinking Fountain (DF) Construction
January 2024 to December 2024
Park Improvement Construction(non DF construction)
January 2023 to December 2024
Project Closeout
December 2024 to June 2025